Electrical design and construction of the infrastructure for 165.6kWp of Kingspan Power Panel at Snetterton Business Park in Norfolk, for steel-frame manufacturer AC Bacon Engineering — including full electrical system design and G99 grid connection with UK Power Networks.

Full electrical infrastructure design and grid connection for a commercial solar installation at Snetterton Business Park, Norfolk.
AC Bacon Engineering — a long-established Norfolk steel-frame building manufacturer — needed the electrical infrastructure designed and installed for 165.6kWp of Kingspan Power Panel at Snetterton Business Park, just off the A11 between Attleborough and Thetford.
At this scale the panels are the straightforward part. The work that determines whether the system ever generates is everything behind them: the electrical system design, the protection, the metering, and critically the G99 grid connection application to the Distribution Network Operator.
Because this site sits in East Anglia, the DNO was UK Power Networks rather than SP Energy Networks or ENW that we deal with across North Wales and the North West. Different network operator, same process — application, technical review, witness testing and Approval to Connect.
The full electrical package behind 165.6kWp of rooftop generation.
Complete design of the electrical infrastructure supporting 165.6kWp of Kingspan Power Panel — cable sizing, protection, inverter arrangement and metering.
Electrical installation and connection of the Kingspan Power Panel array — an integrated roof and solar system rather than a retrofit mounting frame.
Grid connection application and approval with UK Power Networks, including the technical submission and Approval to Connect.
Full testing and commissioning to BS 7671 18th Edition, with certification issued on handover.
Kingspan Power Panel installed across the roof, with the electrical infrastructure designed and connected by our team.






A fully designed, fully approved, fully generating commercial solar system.
A substantial rooftop array cutting bought-in electricity for an energy-intensive steel fabrication and business park operation.
Grid connection secured with UK Power Networks — designed, submitted and approved, so the system exports legally and earns Smart Export Guarantee payments.
Electrical design, installation and grid connection delivered by a single contractor rather than split between a designer, an installer and a connection agent.
Norfolk is a long way from Deeside — proof that our commercial solar capability travels, as it has to Southampton, Manchester and Scotland.
Businesses looking at commercial solar tend to focus on panel count and payback. The step that most often delays a project is the grid connection. Every system above 3.68kW per phase needs a G99 application, and the DNO will assess whether the local network can absorb what you intend to export.
Handled properly — with the electrical design done first and the application submitted correctly — it is simply a process with a timescale. Handled badly, it becomes months of resubmissions with panels sitting on a roof doing nothing.
We manage G99 as standard on every commercial installation, whether the DNO is UK Power Networks in East Anglia or SP Energy Networks across North Wales and Cheshire. If you are weighing up commercial solar panel installation in Chester, Deeside, Wrexham or anywhere else, that process is part of the job, not an extra.
41.85kWp · 202441.85kWp of solar PV built into a canopy structure, with integrated amenity and feature lighting.
£65k · 2024320W T5 fluorescent fittings replaced with 140W LED — a 56% cut in lighting load.
We design the electrical infrastructure, submit the DNO application and get you Approval to Connect — for commercial solar across North Wales, Chester and nationwide.